Plans are underway!

 
Timeline
City approves plans to proceed: October 2024
First draft of drawings complete: October 2024
Second draft of drawings complete: December 2024 
Code study complete: January 2025
Schematic pricing complete: March 2025
City approves 100-year lease addendum: August 2025
Design, development, and construction documents: October 2025 [in progress]
Finalize design plans, secure permits, and complete fundraising efforts: Spring 2026
Begin construction and infrastructure upgrades: Spring–Summer 2026

Funding
Anticipated cost: $1.6 million
Raised to date: more than $510,000